Iran restores 20 million cubic meters of daily gas capacity at South Pars
Gholamabbas Hosseini, chief executive of the South Pars Gas Complex, said the restoration of Train 3 at the Phase 6 refinery and Trains 1–4 at the Phase 4 refinery represents a significant step toward strengthening the country’s energy resilience.
The facilities were officially inaugurated online on Saturday at a ceremony attended by the president.
Hosseini said debris-clearing operations began immediately after the US and Israeli attack on South Pars facilities on March 17, with reconstruction work completed in less than three months.
The project involved 3.6 million man-hours of specialized engineering work carried out in three continuous shifts. Workers also removed around 4,300 tons of debris from damaged infrastructure, equipment and structures.
The reconstruction required an investment of approximately 60 million euros and was carried out with the participation of domestic contractors, private-sector investors and engineering consultants.
Hosseini said the achievement was not limited to repairing damaged facilities, but also demonstrated the country's determination to sustain production, safeguard energy security and withstand external threats.